The integrated test and commissioning for Orange Line Metro Train passes the witness test by representatives of project owner
Lahore, May 8, 2020: With the joint efforts of China and Pakistan, the integrated test and commissioning for Orange Line Metro Train project, constructed by CR-NORINCO, passed the witness test by project owner’s representatives (NESPAK &CEC) on Wednesday, May 6, 2020 in Lahore. This marked the satisfactory completion of related scope of work as per the EPC contract which included electrical and mechanical (E&M) installations, system commissioning, test & commissioning and test run.
The confirmation of installation quality as well as system and linkage functioning by the project owner laid a solid foundation for O&M handover of the project, which is of utmost importance for the project to smoothly proceed towards its public launch.
Post a Comment